Scope of works
- To supply material, modification, installation of the Transformer Room Ventilation System at all Transformer Room include cabling works.
- Testing and commissioning to ensure the system effectiveness
Materials
All material shall comply with the specification such as quality, dimension, strength and others. Sample need to be submitted to the Engineer for approval. All the material must follow the specification as per consultant’s approval before any installation.
Equipment / Tools / Machinery (where applicable)
The following lists for equipment / tool that used in the project:
- Rotary Hammer
- Hacking Machine
- Diesel Generator Genset (Ace-Tech)
- Extension Cables c/w RCCB and Socket Outlet
- Vacuum
- Industrial Blower Fan c/w Exhaust Fan Pipe
- PVC Canvas
- General Tool Box
- Marking Tool
- Measurement Tape
- Personal Protective Equipment